YVR International Arrivals
Project Type: International Arrivals Terminal Building
Location: YVR International Airport, Level 2, Vancouver, BC
Construction Budget: $6.5 M
Electrical Budget: $1.2 M
Project Size: 25,000 square foot
General Contractor: Ledcor Special Projects
Completion Date: April 2009 - On Time.

2009 VRCA Gold Award of Excellence for
Electrical Construction <$2 Million

The New International Arrivals Hall was born of the need to provide a visually welcoming space with 24 hour passenger assistance.

Features of the project include a “Log Jam” lighting arrangement as you exit the customs hall. In front of the rock wall feature you will see canoes traveling down a river made of LED lighting and drywall bulkheads.

Preplanning was key in organizing this multi-phased project to work around the nearly 12 million YVR International Arrival passengers who would walk through this space during construction.

A work platform and hoarding was constructed in such a way as to allow passengers to move through the space with little or no disruption. This allowed Bridge to relocate services and rough in lighting while the passengers traveled beneath the space.